Quick Links
SpotOn Counter Station Hardware Setup
Follow the steps below to set up the SpotOn Counter station hardware.
What is in the Aries 8 Box?
Components | Photo |
---|---|
|
What is in the Aries 8 Mount Box?
Components | Photo |
---|---|
|
Installing the SpotOn Counter Hardware
Begin by assembling the Aries 8 Unit (SpotOn Counter) and connecting it to the mounting bracket.
Guide | Visual |
---|---|
1. Locate the Aries 8 unit and dock 2. Line up the six holes on the back of the Aries 8 unit with the 6 tabs on the dock, and slide up to lock to lock into place | |
3. Route the cable on the back of the dock to the right or left, through the channel | |
4. Line up the 3 holes at the back of the dock with the 3 tabs on the front of the mounting bracket, and slide downwards | |
5. Plug the Lan cable into the Lan port, this can be found on the box coming from the cored attached to the dock. Plug in the power cable. | |
Attaching the Adhesive Ring1. Line up the 3 holes on the bottom of the mount with the 3 pegs on the top of the adhesive ring. | |
2. Use the 3 bolts (from the bag) to attach the adhesive ring. Screw them in from the top of the bottom part of the mount. | |
3. To tighten the base to prevent swiveling, use a screwdriver to tighten the horizontal screw located in the photo to the right. |